# When a pay less notice lands, check the process and the figures separately

A pay less notice raises two questions: whether it was given properly, and whether its deductions are right. First save the notice, its attachments and a record of when and how it arrived, then answer each question on its own evidence.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 30 September 2026 · About 2 min readShare

## Why

A notice that cuts your payment invites one of two mistakes. The first is to argue the figures and never check the notice itself. Was it given in time, by the right person, stating a sum and how that sum was calculated? Skip that, and a notice that may not have worked gets paid as if it had. The second is to call the notice invalid for being late, without checking the contract's rules on counting days and serving documents. Then you lose that argument, even though the deductions were wrong anyway. Keep the two questions apart and each gets a proper answer. Your response can then say exactly what you accept, what you dispute and why.

## How do I do it?

1.  Save the notice, its attachments and the email or portal record showing when and how it arrived.
2.  Check the process: which cycle it answers, who sent it and when it arrived against the window. Check that it states a sum and shows how that sum was calculated.
3.  Check the figures: set the notice against your application on the same basis, and match every deduction to its stated reason.
4.  Link each disputed quantity, rate or item to the drawings, instructions and records that support your figure.
5.  Send a dated response saying what you accept, what you dispute and on what evidence.
6.  Take advice promptly if a date may already have passed.

Our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) examines the notice position and disputed valuation separately before an underpayment is pursued.

If your checks show the notice or its deductions are wrong, see [how to challenge a pay less notice](<https://www.quantsurv.com/underpaid/faq/how-to-challenge-a-pay-less-notice>).

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)