# Attach the back-up before anyone asks for it

Attach evidence suited to the contract's valuation rules: measures, relevant cost records, instructions and dated photographs. Index it to the application lines so the assessor can check the basis efficiently.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Missing or unindexed support can delay assessment or leave a quantity, materials item or variation disputed. The evidence needed depends on the valuation basis: a measured-rate item does not necessarily require an invoice for every input. Provide the relevant records with the application, and answer genuine queries promptly. Further support or an agreed correction may still be possible within the cycle; it does not invariably have to wait until next month.

## How do I do it?

1.  Name every photograph and ticket by the line it proves when you take or receive it, not at month end.
2.  Attach the measure or marked-up drawing that supports every measured quantity.
3.  Attach invoices, delivery evidence or other records where the materials or plant valuation basis requires them, and the relevant instruction and work records for variations.
4.  Attach the dated progress photographs for the period, indexed to the areas they show.
5.  Add a reference column beside the quantities, and check that every line that moved has at least one reference.
6.  Send the back-up as a numbered appendix with a contents page, so each reference in the application opens one document.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) connects the application total to measurements and records that explain the valuation.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)