# They've served nothing, and we didn't know we could serve our own

Nothing has come back from the payer, and we have just found out we may be able to send our own notice.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

If the payer sends no payment notice, [section 110B of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>) may let you send your own. This is often called a default payment notice: your notice of the sum you consider due and how you worked it out.

Whether you need one depends on your contract and your application. If your application was sent as the contract requires, it may already count as your notice, and you do not send a second one. If it does not count, you may need a separate notice. Every day you wait after the payer's deadline pushes the final date for payment back by a day.

A template cannot tell you any of that. Send the wrong notice, or send it the wrong way, and you can lose the cycle or delay your own payment. Check the dates, the form and how it must be served first. Take advice on anything disputed before you send it.

## What do I need to do?

1.  Check the complete payment cycle and whether your application already operates as the relevant notice.
2.  If a separate default notice is needed, verify its permitted route, required content and timing.
3.  State the sum and calculation basis, obtain any necessary advice and serve the document correctly.
4.  Retain service evidence and recalculate the final date where the applicable mechanism requires an adjustment.

To have this done for you, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.

If your application may already stand as the notified sum, see [what to do when no notice came at all](<https://www.quantsurv.com/underpaid/problems/no-notice-came>).

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)