# Their payment notice is wrong and the final date is days away

Their payment notice values our work well below the application, and the final date for payment is close.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A payment notice is the notice the payer sends after your application, saying what it thinks is due and how it worked that out. Under [section 110A of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>), a valid notice fixes the notified sum, even when it undervalues your work. Check the required sender, sum, basis, timing and valid service together before reaching a conclusion.

Emailing to say the notice is wrong does not change that. The Act gives you no counter-notice to send. So there are two questions. Was the notice valid and in time? If not, your application may stand as the notified sum. Is its valuation right? If not, you argue that in your next application or, where the sum justifies it, in an adjudication on the true value.

Both questions need the same papers: your application as sent, the notice with the record of when it arrived, the contract dates and your measure. Get them together before the final date for payment. Check what was actually paid. A correction, agreed interim payment or appropriate dispute route may be possible without waiting for another cycle.

## What do I need to do?

1.  Keep the notice and its service record, and check the sender, timing, sum and calculation basis.
2.  If its effect is uncertain, check whether your application can operate as a default notice or a further notice is required.
3.  Reconcile disputed quantities, rates and deductions against the records rather than treating every difference as an unpaid debt.
4.  Record the response, payment dates and next action, with advice on any disputed statutory or contractual mechanism.

To have this done for you, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) and [Payment evidence process setup](<https://www.quantsurv.com/claims#client-types>) services.

If the notice was late or never came, see [what to do when no payment notice or pay less notice came](<https://www.quantsurv.com/underpaid/problems/no-notice-came>).

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110A (Payment notices: contractual requirements)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)