# A pay less notice has landed and gutted my payment

The number in the notice is a fraction of what we applied for, and the reasons look thin.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

The payer has sent a pay less notice: the notice it must send if it plans to pay you less than the sum already notified. Under [section 111 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>), it has to arrive in time. It also has to state the sum the payer thinks is due and how that sum was worked out.

That gives you two separate questions. Was the notice given properly: by the right person, in time, with a sum and a basis, and sent the way the contract requires? And are the deductions right? A notice can fail on one question and pass the other. The heading on the document decides neither.

If you argue only the figures, a notice that may not have worked gets paid as if it had. If you do nothing before the final date for payment, the lower figure is paid and the difference waits. Adjudication is not your only next step: a question, a written response or a fuller claim may come first.

## What do I need to do?

1.  Save the notice, attachments and evidence of when and how they arrived.
2.  Check the sender, service method, deadline, stated sum and calculation basis against the applicable requirements.
3.  Compare each deduction with your valuation and supporting records, separately from the notice-validity question.
4.  Prepare an evidenced response and obtain prompt advice on disputed notice effects or live deadlines before choosing the next action.

To have this done for you, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) and [Payment evidence process setup](<https://www.quantsurv.com/claims#client-types>) services.

For what to check on the notice and each deduction, see [what to check when a pay less notice is received](<https://www.quantsurv.com/underpaid/tips/check-the-pay-less-notice>).

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.