# We were paid short for months and never checked their notices

The certificates kept coming in low, and we never had time to check whether their notices were even valid.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Each low certificate was paid and the job moved on, so nobody checked whether the notice behind it was valid or in time. Some of those cycles may still owe you money. But a low certificate on its own does not prove that. Later certificates, payments, credits, settlements or decisions may have changed the balance.

So each cycle has to be rebuilt, one at a time. Keep every application, notice, proof of sending, valuation, payment record and agreement. Then separate two questions: what the documents show, and whether it is worth pursuing now, given the cost and the legal position.

Older cycles may raise time limits, known as limitation, or questions about what was agreed or relied on since. Your solicitor has to answer those, and you decide whether a claim is worth it. Leave it too long and the records go missing, the people move on and more cycles run up against the time limit.

## What do I need to do?

1.  Rebuild each cycle from the applications, notices, service records and bank receipts.
2.  Reconcile cumulative figures so later corrections and payments are not counted as separate losses.
3.  Separate notice issues from valuation disagreements and list the evidence for each remaining shortfall.
4.  Obtain advice on deadlines and available routes before deciding which supported items to pursue.

To have this done for you, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) and [Payment evidence process setup](<https://www.quantsurv.com/claims#client-types>) services.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)