# I've had no payment notice, no pay less notice, just silence

The notice windows have passed and nothing has come back from the payer.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

The payer has sent no payment notice and no pay less notice. Your application may then become the notified sum: the figure it must pay by the final date for payment. That is the default route in [section 110B of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). But it only works if your application counts as the notice under your contract. So silence is a reason to check, not a result.

Check the basics first. Was the application sent on the right date, to the right person, in the right form? Did a notice arrive by another route, such as a portal? Have later payments, assessments or agreements changed the account? An older cycle may also raise time limits or other legal questions that one missing email cannot answer.

Get it right and the full application is payable now, with the valuation argued later. Get it wrong and a demand for the full sum fails on the first reply, and costs you credibility for the next cycle. Take advice on the legal route before you call a balance recoverable.

## What do I need to do?

1.  Gather your application, contract dates, proof of service and all notices or portal entries.
2.  Establish whether the application meets the relevant requirements and whether any valid notice changes the payment position.
3.  Check the notified sum and final date before making a written demand. Do not assume silence alone establishes the amount due.
4.  If payment remains withheld, assess proportionate options and any legal deadlines with your adviser.

To have this done for you, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) and [Payment evidence process setup](<https://www.quantsurv.com/claims#client-types>) services.

Before relying on the silence, see [what to check when no payment notice is received](<https://www.quantsurv.com/underpaid/tips/confirm-the-silence>).

If your application may not count as the notice, see [whether you can serve your own](<https://www.quantsurv.com/underpaid/problems/serve-your-own-notice>).

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)