# Our applications have always been paid, so nobody has checked they're valid

It works until the month someone reads the payment clauses and finds the form, the route or the named recipient was never right.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Being paid every month shows the relationship works. It does not prove your applications meet the signed contract: the right form, the right recipient, the right date and the right back-up.

The gap shows up when something changes: a new commercial team at the payer, a tighter cash position or a disputed cycle. How you have always done it may count as evidence. What it counts for depends on the documents and the facts.

When the payer decides to argue, an application that was never valid may not fix the sum in your favour. That holds even when its own notice is missing. A quiet month is the time to compare your routine with the signed terms and fix the gaps. That will not answer every legal point, but it removes the easy arguments.

## What do I need to do?

1.  Compare a live application with the contract's date, form, recipient, amount, basis and service requirements.
2.  Record each gap between current practice and the written terms.
3.  Agree who prepares, checks, approves and serves the corrected document.
4.  Test the next cycle and retain its issue evidence; a compliant previous application does not establish compliance for a later one.

To have this done for you, see our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) service.