# We're referring an underpayment to adjudication and don't know how the 28 days run

The notice of adjudication is going in and nobody has mapped the timetable.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Adjudication is the fast way to get a construction payment dispute decided, usually within 28 days of the referral. Under [Part I of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I>), the timetable runs from the actual documents. Those are the notice of adjudication, the appointment, the referral and the adjudicator's directions. It does not run from a standard calendar.

Several documents may arrive together, and each may have its own deadline, recipient or consent. The parties may agree an extension, or the adjudicator's directions may change the order. An argument about jurisdiction, service or appointment does not by itself move a deadline. Continue to protect the applicable timetable unless it is validly changed. A rule of thumb remembered from the last one is not safe.

Miss a date and a document may go in late, or your figures may not be ready when the referral goes in. What you need is one accurate worksheet, owned by whoever is conducting the adjudication for you, with every document, recipient, consent and deadline on it.

## What do I need to do?

1.  Collect the notice, appointment, referral, directions and any agreed extensions.
2.  Have your adjudication representative confirm the actual timetable, recipients and procedural requirements.
3.  Work backwards from their deadlines to allocate preparation and checking of the financial evidence.
4.  Track every issue and receipt. Seek clarification of changed directions promptly rather than relying on a generic calendar.

To have this done for you, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.

For the standard timetable in outline, see [how long construction adjudication takes](<https://www.quantsurv.com/underpaid/faq/how-long-does-construction-adjudication-take>).

## Sources

1.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part I (Adjudication)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)