# Who issues a pay less notice?

The payer, as the payer, or a person your contract names to send it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 1 min readShare

## The answer

The payer, as the payer, or a person your contract names to send it. That is the rule in [section 111 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). So find the payment the notice relates to, and check where the sender's authority comes from in your contract. Do not go by the organisation chart or by who is more senior. Judge the document on what it says and whether it meets the rules, not on its heading. And note that disagreeing with a valuation does not, on its own, give you a right to suspend work.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) records who is authorised to issue the notice and how approval and service are handled.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.