# What must a payment notice include under the Construction Act?

It must state the sum considered due at the payment due date and the basis of calculation. The mechanism determines whether the payer, named person or payee gives it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

A payment notice must state the sum considered due at the payment due date and the basis of calculation. The mechanism determines whether the payer, named person or payee gives it. That is the rule in [section 110A of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>).

In practice, check that the notice you receive also shows who sent it and to whom. It should name the contract, the cycle and the application it answers. It should show the total value to date, what has already been paid and the balance now due.

An itemised explanation helps make deductions checkable, but the statutory test is the sum and basis; there is no universal separate evidence attachment or detailed-reasons requirement for every line.

If no notice arrives, your contract may give you a default route, but check it against the contract rather than assume it.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) helps prepare or check the stated sum and its calculation basis against the actual payment mechanism.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110A (Payment notices: contractual requirements)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>). legislation.gov.uk.