# What is a pay less notice?

A pay less notice is the notice the payer must send if it plans to pay you less than the notified sum.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 15 October 2026 · About 3 min readShare

## The answer

A pay less notice is the notice the payer must send if it plans to pay you less than the notified sum. You will also see it written as one word, a payless notice; it is the same notice.

## What must the notice say?

It must state the sum the payer thinks is due on the date of the notice, and how that sum was worked out.

## When and how is it served?

If your contract sets no deadline, [Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II>) fills the gap. Our [guide to the Scheme](<https://www.quantsurv.com/library/scheme-for-construction-contracts>) explains when it applies. Its deadline is 7 days before the final date for payment. Do not assume the Scheme's period applies to your job; check your contract first.

## What does it change?

A missed payment notice does not always stop the payer sending a valid pay less notice, so check that deadline too. The notice should tie the lower sum back to the payment record, with each deduction explained. A valid pay less notice lowers what must be paid this cycle. It does not cancel your evidence or decide what the work is finally worth.

## What records should you keep?

Preserve the notice, attachments, email headers and service evidence. Record which payment cycle it concerns, the amount stated and the explanation of that amount.

Compare its timing using the [payment dates calculator](<https://www.quantsurv.com/library/tools/payment-dates-calculator>), then examine content and service separately. A timely document can still raise content questions, and disagreement with its valuation does not by itself make it invalid.

## Example

### The facts

The notified sum for the cycle is £120,000. Your main contractor's pay less notice takes off £9,000 for an item they dispute. You check the notice before you accept the lower figure.

### What happens

1.  You work out the deadline for the notice from the final date for payment and your subcontract.
    
2.  You check who sent it and how it was sent against what your subcontract requires.
    
3.  The notice states £111,000, and you check it shows how that was worked out, with the documents behind it.
    

### The notice in figures

| Item | Amount |
| --- | --- |
| Notified sum | £120,000 |
| Disputed item | £9,000 |
| Sum stated in the pay less notice | £111,000 |

### What this shows

The notice states £111,000: the £120,000 less the £9,000 disputed. That is the arithmetic only. Whether the notice works depends on your subcontract and the law that applies.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) supports the valuation and supporting records behind the proposed payment position. For a contested position: If one has cut your payment and the final date is close, [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) assesses the notice and supporting figures within the scope and timetable agreed with you.

## Sources

1.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II (Payment)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II>). legislation.gov.uk.