# How do JCT pay less notices and payment notices work?

Your JCT contract determines who gives each notice and when. Check the form, edition and amendments; a main-contract Interim Certificate does not automatically fix a subcontract payment.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

In the SBC/Q 2016 main contract, an Interim Certificate has a payment-notice function. That is useful context for clause searches, but the parties, documents and timetable under your own contract must be identified separately. Your payer is normally the main contractor, not its client or architect.

For an in-scope contract, [Housing Grants, Construction and Regeneration Act 1996, section 110A](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>) requires the relevant payment notice to state the sum considered due and its basis. If the payer or named person misses the required notice, [section 110B](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>) may allow your compliant application to operate as the default notice or require a further payee notice. A later default notice can postpone the final date. Silence alone is not enough: check content, timing, service and the mechanism.

A valid [pay less notice](<https://www.quantsurv.com/underpaid/faq/what-is-a-pay-less-notice>) can reduce the amount payable from the notified sum under [section 111](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). Check its sum, basis, authority, service and separate deadline. A document's label does not conclusively establish its function: a late payment notice may require assessment as a possible pay less notice if it satisfies that different test.

Keep the notice issue separate from whether the underlying measure, rate or deduction is right. Preserve the exact files and service records and record the sum applied, notified, payable after any valid pay less notice, and actually received.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) turns the signed JCT payment provisions into a calendar of preparation, assessment and notice responsibilities.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110A (Payment notices: contractual requirements)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). legislation.gov.uk.
3.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.