# How to challenge a pay less notice

Keep the notice and the proof of when it arrived, then challenge the notice itself and its deductions as two separate questions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 3 min readShare

## Before you start

Gather the agreement, application, payment notices, attachments, service records and receipts. Identify any live response or challenge deadline first. An informal request for an explanation does not extend it.

## Step-by-step guide

1.  ### 1. Preserve the payment record
    
    Keep the notice exactly as received, including attachments and evidence of when and how it arrived. Identify the payment cycle and keep the application, notified sum and receipts as separate amounts.
    
2.  ### 2. Check the notice requirements
    
    Check the sender and authority, service method, deadline, valuation date, sum and calculation basis against the actual agreement and applicable law. Obtain advice on any disputed effect before assuming the notice is ineffective.
    
3.  ### 3. Test each deduction separately
    
    Compare each deduction with the contract, measurement and supporting records. Show the other party's amount, your supported amount, the difference and evidence needed. Winning on a notice point does not automatically establish the value of the work.
    
4.  ### 4. Prepare the response and decide the next step
    
    Set out notice issues separately from valuation objections. Retain the response and service evidence. Take advice on remedies, jurisdiction and the order of steps, and assess cost and proportionality before choosing a dispute route.
    

**Before you finish:** The file should show the checked timetable, notice findings, deduction schedule, remaining uncertainties and approved next action.

## Worked example

### The facts

You apply for £85,000 and a pay less notice states £60,000. You want to test both the notice and the £25,000 of deductions before deciding what to do.

### What happens

1.  You keep the original notice and the record of when it arrived.
    
2.  You check the notice against your subcontract: sender, deadline, valuation date, sum, calculation and how it was sent.
    
3.  You test the £25,000 of deductions separately, against your measure and your records.
    
4.  You record the findings and open questions, prepare the response and obtain advice on the next action before any applicable deadline.
    

### The notice in figures

| Item | Amount |
| --- | --- |
| Application | £85,000 |
| Notice | £60,000 |
| Deductions tested | £25,000 |

### What this shows

The file sets out each finding and each open point. It does not predict whether the challenge to the notice or to the valuation will succeed.

If the notice has only just arrived, start with [what to check when a pay less notice is received](<https://www.quantsurv.com/underpaid/tips/check-the-pay-less-notice>).

If you are weighing a challenge, [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) tests the notice and values each deduction, supporting your decision about proportionate next steps.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)