# How long does construction adjudication take?

Under the Construction Act framework, the usual decision period is 28 days from referral. It can extend by 14 days with the referring party's consent, or further by both parties' agreement.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 7 October 2026 · About 2 min readShare

## The answer

Under the Housing Grants, Construction and Regeneration Act 1996 framework, the usual decision period is 28 days from referral. It can extend by 14 days with the referring party's consent, or further by both parties' agreement.

[Section 108 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/108>) sets a short, fixed timetable. You serve a notice of adjudication. The adjudicator is appointed, and the referral goes to them, within 7 days of that notice. The adjudicator must then decide within 28 days of the referral. You, as the referring party, can agree to extend that by up to 14 days. It can go longer only if both sides agree. Our [adjudication timetable](<https://www.quantsurv.com/library/tools/adjudication-timetable>) counts these dates from your notice.

Inside the 28 days the adjudicator sets deadlines for the response, a reply and sometimes a further reply, often a week apart, and may hold a meeting. If the losing side does not pay, enforcing the decision in court is a separate step that usually takes several more weeks.

The real time goes into preparation before the notice. Both parties need an indexed file and figures that can be checked within the directions. The actual response timetable varies; preparation improves the ability to present the evidence but does not decide the result.

If a referral has already landed, see [how to map the 28 days from the actual documents](<https://www.quantsurv.com/underpaid/problems/how-the-28-days-runs>).

[Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) builds the documents and the figures before the clock starts.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 108 (Right to refer disputes to adjudication)](<https://www.legislation.gov.uk/ukpga/1996/53/section/108>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)