# How late can a pay less notice be served?

By the deadline in your contract, counted back from the final date for payment; the Scheme's 7 days applies only if your contract sets none.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

By the deadline in your contract, counted back from the final date for payment; the 7-day period under the Scheme for Construction Contracts (England and Wales) Regulations 1998 applies only if your contract sets none.

The 7 days comes from [paragraph 10 of Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II/paragraph/10>). It is not a fixed period under [the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/part/II>), the [Construction Act](<https://www.quantsurv.com/library/construction-act>). Many contracts set their own period. For example, the JCT Standard Building Contract With Quantities 2016 uses 5 days before the final date for payment.

A notice sent too early may have no notified sum to reduce yet. One sent after the deadline may not work at all. The notice should name the cycle it answers and state the sum due on its own date.

To check the payer's notice, work out the last day it could arrive. Use the actual final date for payment, the notice period and the rules on when a notice counts as served. Check whether your contract counts calendar days or working days. Do not count a statutory deadline in working days without checking the counting rules.

Our [payment dates calculator](<https://www.quantsurv.com/library/tools/payment-dates-calculator>) counts them for one payment cycle. Keep your calculation with the evidence of when the notice arrived.

If you are not sure a notice is needed at all, see [when a pay less notice is needed](<https://www.quantsurv.com/underpaid/faq/when-do-you-issue-a-pay-less-notice>).

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) derives the notice window from the relevant cycle and preserves the service record.

## Sources

1.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 10 (Notice of intention to pay less than the notified sum)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II/paragraph/10>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, Part II (Construction contracts), as amended by the Local Democracy, Economic Development and Construction Act 2009, Part 8](<https://www.legislation.gov.uk/ukpga/1996/53/part/II>). legislation.gov.uk.