# What is the difference between a payment notice and a pay less notice?

A payment notice sets the sum due for the cycle; a pay less notice says the payer plans to pay less than that sum.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 3 min readShare

## The answer

A payment notice sets the sum due for the cycle; a pay less notice says the payer plans to pay less than that sum. They do different jobs at different times.

The applicable payment notice states the sum considered due at the due date and its basis. Check the actual mechanism and timing: it is not universally a notice sent after the due date, and a payer notice is not a prerequisite to every pay less notice.

The pay less notice is different. Under [section 111 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>), it states what the payer considers due on the date it is sent. It has its own deadline, usually counted back from the final date for payment.

Each must state a sum and how it was worked out. A payment notice lower than your application does not need a pay less notice as well. A pay less notice is only needed if the payer wants to pay less than the notified sum. Keep your application, the notified sum and the amount paid as separate figures in your records.

## Key differences

Scroll across to read all columns.

The difference at a glance
| Point | Payment notice | Pay less notice |
| --- | --- | --- |
| Purpose | Sets the notified sum for the cycle. | States the sum considered due at the notice date where the payer intends to pay less than the notified sum. |
| Valued at | The payment due date. | The date the notice is sent. |
| Sent by | The payer or the person your contract names. Some contracts make you send it. | The payer or a person it authorises under your contract. |
| Deadline | The applicable contractual/statutory timing, no later than five days after the due date where section 110A applies. | Its own window, often counted back from the final date for payment. |
| Must show | The sum and how it was worked out. | The sum considered due at the notice date and the basis of calculation; itemised deductions help explain that basis. |

## Example

### The facts

You apply for £80,000. Your main contractor's valid payment notice states £68,000 at the payment due date.

### What happens

1.  If they pay the £68,000, no pay less notice is needed, even though the notice is lower than your application.
    
2.  If they want to pay £64,000 instead, they need a valid pay less notice in time, and you check that they sent one.
    
3.  The payment notice does not cover the further £4,000 cut on its own.
    

### The sums in question

| Item | Amount |
| --- | --- |
| Application | £80,000 |
| Payment notice | £68,000 |
| Lower sum your main contractor might want to pay | £64,000 |

### What this shows

The £68,000 payment notice stands on its own. Only a plan to pay less than that, such as £64,000, needs a pay less notice and its deadline.

The figures show the difference, not a verdict on a live notice.

If you have been paid less than the notified sum, see [when a pay less notice is needed](<https://www.quantsurv.com/underpaid/faq/when-do-you-issue-a-pay-less-notice>).

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) records the separate purpose, sender and deadline for each notice rather than treating them as interchangeable.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.