# Can the payer re-issue its payment notice?

Possibly, but it cannot backdate it, so keep every version and check whether the deadline was still open when the new one arrived.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## The answer

Possibly, but it cannot backdate it, so keep every version and check whether the deadline was still open when the new one arrived. A notice already sent cannot be quietly overwritten. Check your contract for any right to correct a notice, the deadline the notice had to meet and what the change does to your payment. Paying you an extra amount nobody disputes is not the same as changing the notice itself. If the window has closed, a later pay less notice may still be open to the payer. Some contracts allow no correction at all. Get advice quickly on the actual documents.

To have a replaced or corrected notice tested against the window it had to meet, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)