# Can the payer re-issue or withdraw its pay less notice?

A replacement only counts if it was allowed and arrived before the deadline, so keep the original and check the dates.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## The answer

A replacement only counts if it was allowed and arrived before the deadline, so keep the original and check the dates. Any replacement should show the date it was actually sent and say which notice it replaces. It must come from the right person, contain what a pay less notice must contain and be sent the way your contract requires. It cannot be backdated. If the payer withdraws a deduction and pays you more, that does not by itself change the status of the notice. Once the deadline has passed, write down your commercial and legal options separately, and take advice on the actual documents.

To have a corrected or withdrawn pay less notice tested against the deadline it had to meet, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.