# Can a payment notice show a negative valuation?

A negative figure in a payment notice and a right to demand money back from you are two different questions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## The answer

A negative figure in a payment notice and a right to demand money back from you are two different questions. A negative figure means the payer says it has paid you more than the work is worth to date. Whether the notice should show a negative sum depends on your contract and the law that applies. So do whether you must repay anything and how it could be recovered. So do not repay anything, and do not assume a negative figure simply counts as nil, until it has been checked. First reconcile the value of the work, the adjustments and the payments against your own records. Then have the notice and any repayment demand checked.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) checks the cumulative valuation, previous amounts and adjustments before a negative assessment is relied on. For a contested position: To have a negative notice reconciled against your own records before anything is repaid or conceded, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.