# Can I resubmit a payment application after a payment notice?

You can send more evidence and ask for a review, but that does not replace your application or restart the notice deadlines.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

You can send more evidence and ask for a review, but that does not replace your application or restart the notice deadlines. Nor does it change a notice already sent or move the final date for payment.

Consider separately whether the new evidence supports a higher valuation and whether the current cycle can accommodate a correction or extra payment. If it cannot, establish what should go into your next application.

It is not automatically true that you must wait for the next cycle. Nor must the payer revalue before the current final date.

If it accepts the extra amount, record the amount and when it will be paid. If it is still disputed, send a reasoned valuation response. Take legal advice where the notice's effect, your right to be paid or the dispute procedure is contested. A missing written instruction does not always mean a variation has no value or no right to payment.

For a notice already received and a deadline close, use [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>).

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)