# Can an email be a valid pay less notice?

It can be, but it depends on your contract's notices clause, and the email must still say what a pay less notice must say.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 12 October 2026 · About 2 min readShare

## The answer

An email can serve as a pay less notice if your contract's notices clause permits it and the email contains the required information. Read the clause for the email address or platform it names, who may send notices and when a notice counts as received.

Where [section 115 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/115>) applies and the parties have not agreed how notices are sent, any effective means will do. So a contract that says nothing about email does not settle the question either way.

The email still has to state the sum and how it was worked out. Keep the message, the attachment, the email headers and any receipt. If service or effect is disputed, have the notice and the contract checked rather than treating email as automatically valid or invalid.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) checks the permitted communication method and evidence needed for routine service. For a contested position: To have the service of a notice tested against your contract's notices clause, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 115 (Service of notices, &c.)](<https://www.legislation.gov.uk/ukpga/1996/53/section/115>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)