# Can a payment notice be a pay less notice?

Possibly, but a line saying 'treat this as a pay less notice too' does not make one document work as both.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 1 min readShare

## The answer

Possibly, but a line saying 'treat this as a pay less notice too' does not make one document work as both. Equally, one email is not always incapable of doing both. And a pay less notice does not always have to follow a payment notice.

Each role has its own purpose, content, valuation date, deadline and service rules, and the document must meet each one. Keep the document exactly as it was sent. Where both roles are being relied on, have it checked against your contract.

The case of [Placefirst Construction Ltd v CAR Construction (North East) Ltd](<https://caselaw.nationalarchives.gov.uk/ewhc/tcc/2025/100>) \[2025\] EWHC 100 (TCC) shows why the facts and the actual emails matter. See especially paragraphs 37, 40 and 52. It is not permission to use a combined template.

To have a combined notice tested for each role it claims to play, see our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) service.

## Sources

1.  [Placefirst Construction Ltd v CAR Construction (North East) Ltd \[2025\] EWHC 100 (TCC) (High Court, Technology and Construction Court, 24 January 2025)](<https://caselaw.nationalarchives.gov.uk/ewhc/tcc/2025/100>). The National Archives, Find Case Law.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)