# Record the works as they stand on the termination day

The moment another firm starts finishing your work, the evidence of what you left behind starts to disappear, so record it on the termination day.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Every figure in a termination account starts from what was on site on the termination day: work done, materials fixed, materials stored and plant left behind. Within a week the completion contractor, the firm brought in to finish, has built over some of it, moved the rest and started its own records. Those records describe the site as it found it. With no record of your own, you are left valuing your work from your last application and memory. The other party values it from what its completion contractor says was missing. A dated record made on the day, or as close to it as access allows, is the one piece of evidence the other side cannot produce.

## How do I do it?

1.  Ask in writing for access on the day, or the next working day, to record the works. Keep the request if access is refused.
2.  Photograph every area with the date and location, and mark up a set of drawings showing what was complete, part complete and not started.
3.  List the materials on site and off site with their delivery tickets, and the plant and equipment left behind.
4.  Keep the record with the termination documents, dated and untouched, and do all later work on copies.

Our [Termination account preparation and assessment](<https://www.quantsurv.com/claims#client-types>) uses the termination-day record to distinguish completed work, materials and the remaining scope.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)