# Answer a default notice in writing, inside its period

A default notice gives you only days to answer, and silence leaves the other party's version of the facts as the only one on file. A written reply inside the period, with your records attached, puts your side next to it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

A default notice is usually the first formal step towards termination, and the period it gives you is short. Where a contractual default remains unremedied after the applicable period, a further termination step may become available. A written answer alone is not the same as remedying the default. The file then holds only its account of why. A written reply showing the resources on site, the access given and the directions dealt with gives it a reason to think again. If it does not, your solicitor has the facts to work with. The reply costs a morning; silence can cost the rest of the contract.

## How do I do it?

1.  Send the notice for prompt legal review. Verify the clause, service date, trigger, day-count rule and required remedial action before calculating the deadline.
2.  Gather the records that answer the default named: labour returns, diaries, access and release dates, and what was done about each direction.
3.  Write the reply within the period: the facts, the records attached, and what you are doing now, without arguing the law.
4.  Send the notice and the reply to your solicitor the same day, and put the date a termination notice could follow in the diary.

Our [Termination risk review and escalation setup](<https://www.quantsurv.com/claims#client-types>) organises the notice, response and evidence of performance while legal questions are escalated to the appointed solicitor.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)