# They terminated us out of the blue, with no default notice first

There was no warning and no chance to put anything right, just a letter ending the contract and telling us to leave site.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Most contracts only let the other party terminate for your default by set steps. First a notice naming the default, then a period to put it right, then a further notice. A letter that ends the contract with no default notice first, or on a ground the contract does not list, may not follow those steps. Some amended contracts also allow the contract to be ended without any default, with their own payment rules. The wording decides which you are dealing with.

If the termination was not valid, it may itself be a breach of your contract. Identify the available legal and contractual basis before valuing unpaid work, wasted commitments or lost net profit. Calculate remaining revenue less avoided costs, allow for mitigation and avoid claiming the same loss twice. A valid termination follows the applicable account provisions; completion costs are not automatically chargeable under every termination ground.

Whether it was valid is a legal question, and the answer can take time. The figures cannot wait. They come from the same records either way. And the evidence of what was on site starts disappearing the day another firm arrives to finish your work.

## What do I need to do?

1.  Send the termination letter, earlier notices and agreement to your solicitor immediately.
2.  Preserve evidence of the works, unpaid balance and outstanding commitments.
3.  Prepare separate supported figures for the potentially applicable termination and loss positions.
4.  Keep validity and valuation distinct and follow advice before taking further irreversible steps.

To have this done for you, see our [Termination account preparation and assessment](<https://www.quantsurv.com/claims#client-types>) and [Termination risk review and escalation setup](<https://www.quantsurv.com/claims#client-types>) services.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)