# My contract has been terminated and they want me to pay to finish it

We've been put off site, our last application hasn't been paid, and now there's a bill for someone else to complete our work.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Termination changes how the money works. Default-termination provisions may defer aspects of the account, but do not assume all payments stop. Check the actual clauses alongside accrued payment rights, statutory requirements and the stated termination ground. Then an account is drawn up. It sets what the whole package would have cost under your contract against what the other party has paid you and spent finishing it. The balance goes whichever way it falls.

The other party brings in another firm, the completion contractor, to finish your work. What that costs, the cost to complete, is where these accounts grow. The price can include betterment, meaning a better specification than your contract asked for, plus work outside your package and extras the other party wanted anyway. Your own work, meanwhile, is often valued by the other party's surveyor after you left, with nobody measuring on the day.

Whether the termination was valid is a question for your solicitor, and it matters: if it was not, the account may look very different. But the figures on both sides have to be built either way. If nobody answers the other party's figures, they are the only ones on the table. And the evidence of what you left on site starts disappearing the day the completion contractor arrives.

## What do I need to do?

1.  Record the state of the works and available materials at termination.
2.  Measure your work and variations and reconcile them against payments under the termination-account provisions.
3.  Compare replacement costs with the original scope, identifying betterment, unrelated work and duplication.
4.  Prepare the supported account with assumptions and disputed legal questions clearly separated.

To have this done for you, see our [Termination account preparation and assessment](<https://www.quantsurv.com/claims#client-types>) and [Termination risk review and escalation setup](<https://www.quantsurv.com/claims#client-types>) services.