# They're building a case to terminate us, and my site team hasn't noticed

Progress complaints, directions to redo work and letters to the company are landing on site, and none of it gets past the cabin.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Your site team can deliver good work while the paper that decides a termination passes it by. A direction to remove defective work is agreed on the walkround and never done. A letter addressed to the company sits on the cabin desk. A complaint about progress gets answered by phone, with nothing in writing.

Each one is small on its own. Put together, they are what the other party needs for a default notice, the formal warning that comes before termination. And a notice left in the cabin can use up most of its short period before the office even sees it.

## What do I need to do?

1.  Identify the notices and directions that may start a default or remedy period.
2.  Give the team a short instruction sheet naming the recipient, escalation route and deputy.
3.  Escalate formal notices immediately and keep a record of receipt and required action.
4.  Use periodic reviews to check that correspondence was dealt with, without delaying urgent action until the meeting.

To have this set up for you, see our [Termination risk review and escalation setup](<https://www.quantsurv.com/claims#client-types>) service.