# I've been sent a default notice

The other party says we are in default and has given us a few days to put it right, or it will terminate.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A default notice is usually the first formal step towards termination. Under most contracts, it must name the default, a breach the contract lists, and give you a set period to end it. If the default carries on past that period, the other party can terminate by a further notice. The period is short, often days rather than weeks. Its start and end depend on the actual clause and service provisions, which may include deemed service. Do not count from when the office happens to read it.

The defaults named are ordinary events on a hard job: progress said to be too slow, defective work not removed when directed, a gang taken off site. Some notices are well founded; others are pressure. Either way, silence is the worst answer. It leaves the other party's version of the facts as the only one on file, and the clock keeps running.

## What do I need to do?

1.  Preserve the notice and service evidence and send the contract and correspondence to your solicitor promptly.
2.  Confirm the alleged default, trigger, remedy period and any potential termination timetable.
3.  Gather records answering the allegation and take any required remedial action within the actual period.
4.  Issue the supported response and retain evidence of the remedy; a reply alone does not cure a default.

To have this set up for you, see our [Termination risk review and escalation setup](<https://www.quantsurv.com/claims#client-types>) service.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)