Source: https://www.quantsurv.com/termination/faq/termination-for-convenience
Content format: Markdown version of the public page.
Content reviewed: 2026-10-12

# What does termination for convenience mean for my contract?

It means the other party can end your contract without any default by you, but only where your contract says so.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 12 October 2026 · About 2 min readShare

## The answer

A termination-for-convenience clause can allow the other party to end your contract without any default by you, but only on the terms your contract provides. Check the actual form, edition and amendments for an express convenience right and its scope; do not infer it solely from the JCT or NEC label or the main contract.

Without one, ending your contract for no good reason is likely to be a breach. With one, the question becomes what you are paid. The actual clause determines whether and how work done, ordered materials, cancellation, demobilisation or lost profit are valued, including exclusions and conditions.

So read the payment part of the clause first. Then record the works, materials and plant as they stood on the termination day. Value the work done, gather the cancellation charges and the cost of leaving site, and set out any lost profit the clause allows.

Whether the clause was used properly is a question for your solicitor. The account itself is built from your own records.

To have the account after a termination for convenience built and pursued, see our [Termination account preparation and assessment](<https://www.quantsurv.com/claims#client-types>) service.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)
