# Can I terminate my contract if the other party does not pay?

Take legal advice before terminating for non-payment. A contractual termination right and a right arising from serious breach are different questions. Suspension also has conditions and notice requirements; it is not an automatic safe alternative.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Take legal advice before terminating for non-payment. A contractual termination right and a right arising from serious breach are different questions. Suspension also has conditions and notice requirements; it is not an automatic safe alternative. Termination and suspension are distinct routes that need the actual contract and legal conditions checked. Do not simply walk off site.

Your solicitor advises on termination grounds, valid service, any cure period and consequences.

For statutory suspension, assess the amount payable after valid notices and whether it remains unpaid after the final date; a valid pay less notice does not excuse non-payment of the reduced amount. Section 112 requires at least seven days’ notice stating the grounds, subject to the applicable conditions.

Keep the payment and service evidence and obtain advice on the proposed action and restart obligations. [Section 112 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>) sets the statutory suspension framework.

To have your right to suspend or terminate checked, and the notice route set up before anyone leaves site, see our [Termination risk review and escalation setup](<https://www.quantsurv.com/claims#client-types>) service.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 112 (Right to suspend performance for non-payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>). legislation.gov.uk.