# What happens to my money when my contract is terminated?

Payment after termination depends on the grounds, the contract and the applicable law. Some contracts defer further payment and require a completion account; do not assume that every termination stops every payment right.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Under the standard JCT subcontracts, after a termination for your default, the other party finishes the work. It then works out what the whole contract would have cost on your terms. It sets that against what it has paid you, what it spent finishing the work, and any loss the termination caused it. The difference is paid whichever way it falls.

If you terminate for the other party's default, the account runs the other way and can include your own loss. Sums that fell due before the termination may be treated differently, depending on the wording.

Amended and bespoke contracts change the details, so check your termination clauses for the account they require. Retention, materials on and off site and unpaid applications all have to be placed within that account. The records of what was on site on the termination day carry much of its weight, so make them straight away.

Building the account the termination provisions require, and pursuing the balance, is our [Termination account preparation and assessment](<https://www.quantsurv.com/claims#client-types>) service.