# Check the retention on every certificate

Check the retention taken on every certificate against your contract, because the first thing disputed at release is how much is held. A mistake found in month 3 costs a phone call; the same mistake found at release costs an argument.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

Retention is worked out afresh on every certificate, and small errors add up. Common ones are the wrong percentage, or retention taken on sums the contract says are free of it. Others are a limit ignored once reached, or a release never credited. Nobody notices while the job runs, because the sums are small and the cash is flowing. At release, your figure and the payer's differ, the certificates, applications and payment records need reconciling, and rebuilding 2 years of them takes days. A running check, one line per certificate, keeps the figure agreed as it grows.

## How do I do it?

1.  Record the retention percentage, any limit and any sums the contract says are free of retention.
2.  Check the retention taken on each certificate against the gross valuation and the percentage.
3.  Record the cumulative retention balance after each certificate, or add only the incremental deduction and subtract releases. Never sum successive cumulative balances. Reconcile the position with applications and actual payments.
4.  Raise any difference in writing in the same payment cycle, while the certificate is current.
5.  Ask for the sum your running total shows at each release, with the certificate references attached.

Our [Final account preparation and assessment](<https://www.quantsurv.com/quantity-surveying#client-types>) reconciles retained amounts against the agreed percentage, cap and releases throughout the job.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)