Source: https://www.quantsurv.com/retention/tips/ask-for-the-certificate
Content format: Markdown version of the public page.
Content reviewed: 2026-10-10

# Ask for the certificate, not just the money

Identify the certificate or event the release wording refers to, but also check whether that condition is effective. A missing upstream certificate does not automatically mean no retention is due.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Many subcontract releases are tied to a certificate under the main contract: practical completion, or making good at the end of the defects period. You have no part in issuing it, so the release can sit for months while the main contractor and the employer argue about other trades. Ask for the money and you are told the certificate has not been issued. Ask about the certificate and the real questions come out: when it is due, what is holding it, and whether any of those items are yours. Also check the condition under [Housing Grants, Construction and Regeneration Act 1996, section 110](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>) where the Act applies; the effective mechanism may differ from the written upstream link.

## How do I do it?

1.  Find the certificate or event each release depends on, in the contract's own words.
2.  Ask the payer in writing, as the trigger approaches, when the certificate is expected and what, if anything, is holding it.
3.  Ask for the list of items said to be outstanding, and separate yours from other trades'.
4.  Close your own items and confirm in writing, with photographs, that they are closed.
5.  Request the release when due under the effective mechanism, attaching the relevant evidence and addressing any disputed condition.

Our [Final account preparation and assessment](<https://www.quantsurv.com/quantity-surveying#client-types>) identifies which milestone evidence is missing and how it affects the release request. Where the relevant release conditions are met but payment remains withheld, [Retention recovery](<https://www.quantsurv.com/claims/retention-recovery>) assesses the outstanding balance.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>). legislation.gov.uk.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)
