# What is a defects liability period?

It is a contractual period for dealing with defects after completion. The correction process, retention release and wider liability need separate checks.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 12 October 2026 · About 2 min readShare

## The answer

A defects liability period is a contractual period for dealing with defects after completion. The correction process, retention release and wider liability need separate checks. JCT forms use rectification terminology; NEC uses its own defects date and correction provisions. Read your exact contract and amendments rather than assuming a universal twelve-month period.

Record what starts the period, which defects you are responsible for, how they are notified and the time allowed for correction. A final list or certificate may have a role, but neither is required in identical terms on every contract. Keep access offers, completed repairs and disputed allegations on the record.

Retention may depend on a separate release event and payment procedure. If release is tied to performance or certification under the main contract, have the condition checked against [section 110 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>), where applicable. Upstream payment is a separate issue.

Expiry of the correction period does not automatically end liability for a breach or a defect discovered later. A late list is therefore not, by itself, a reason to disregard every allegation.

For how the JCT Standard Building Contract runs the period clause by clause, see [how JCT clause 2.38 works](<https://www.quantsurv.com/retention/faq/jct-clause-2-38-rectification-period-defects>).

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) keeps the relevant dates and defect records aligned with completion and release procedures.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>). legislation.gov.uk.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)