# Are cash retentions in construction being banned?

As checked on 7 October 2026, the Commercial Payments Bill proposes a construction retention ban but has not completed its legislative process.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 1 min readShare

## The answer

As checked on 7 October 2026, the Commercial Payments Bill proposes a construction retention ban but has not completed its legislative process. Parliament’s [Commercial Payments Bill: report stage](<https://www.parliament.uk/business/news/2026/september-2026/commercial-payments-bill-report-stage/>) records Lords report stage on 15 September and third reading scheduled for 20 October 2026. A scheduled stage is not enactment or commencement.

The government's [Commercial Payments Bill: overview](<https://www.gov.uk/government/publications/commercial-payments-bill-factsheets/commercial-payments-bill-overview>) describes the proposed reform and implementation approach. Check the eventual enacted wording, commencement and transitional provisions before changing the treatment of a particular contract. Do not assume the proposal retrospectively releases cash already held.

Continue to record existing retention, verify its release and payment conditions, submit the required requests and check notices and receipts. Seek prompt advice on any finality or limitation issue affecting an old balance.

For existing balances, [Retention recovery](<https://www.quantsurv.com/claims/retention-recovery>) assesses and pursues supported retention claims, while [Retention tracking and release process setup](<https://www.quantsurv.com/claims#client-types>) helps your team track release triggers and prepare timely requests.

## Sources

1.  [Commercial Payments Bill: report stage](<https://www.parliament.uk/business/news/2026/september-2026/commercial-payments-bill-report-stage/>). UK Parliament.
2.  [Commercial Payments Bill: overview](<https://www.gov.uk/government/publications/commercial-payments-bill-factsheets/commercial-payments-bill-overview>). Department for Business and Trade, GOV.UK.