# How does JCT SBC/Q 2016 clause 2.38 work?

JCT SBC/Q 2016 clause 2.38 is a main-contract defects provision. Your own contract determines your remedy obligations and the relevant retention release process.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

If you are working under a contract, read the defects and retention provisions in your executed agreement first. Identify the defects period, who can instruct remedial work, the notice and access requirements, completion evidence and release/payment conditions. Main-contract clause numbers and certificates do not automatically determine your rights.

SBC/Q 2016 clause 2.38 concerns the payer's rectification obligations, with a making-good certificate addressed in clause 2.39. This explains the upstream process, but it does not make you responsible for every item on the project's defects list. Check each item against your scope, workmanship obligations, handover condition and evidence of later damage.

Record the defect, location, instruction, proposed remedy, access and completion evidence. Where the parties agree a deduction instead of remedial work, document the authority, amount and settlement scope. A missed schedule or procedural deadline does not automatically erase an underlying breach or defects liability; its consequences need assessment.

For retention, distinguish your release trigger from the payment due date and final date. Ask for outstanding certificates or confirmation, but have any condition dependent on upstream certification or performance checked against the applicable statutory restrictions. Do not assume that a withheld main-contract certificate can postpone your payment indefinitely.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) records the applicable rectification obligations, notifications and completion evidence.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)