Source: https://www.quantsurv.com/retention/faq/how-to-request-retention-release
Content format: Markdown version of the public page.
Content reviewed: 2026-10-10

# How do I request the release of retention?

Find the release trigger in your contract, then ask in writing once it happens, citing the trigger, the sum held and the sum now due.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Identify the release event and payment mechanism in your executed contract. A release may depend on completion, a defects event or another defined condition, and the release event is not necessarily the payment due date or final date for payment.

Reconcile retention actually deducted and previously released. Send the required application or request through the specified channel, stating the trigger, supporting certificate or other evidence, amount requested and relevant payment period. A general reminder may not satisfy the actual application or notice requirements.

Check the operative payment notice and any pay less notice. A valid payment notice may already establish a lower notified sum; a timely pay less notice is required where the payer intends to pay less than the notified sum under [Housing Grants, Construction and Regeneration Act 1996, section 111](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). Whether the underlying retention valuation is correct and whether the notice is valid are separate questions.

Where a certificate is missing, identify who should issue it and request the necessary action. Also have any condition tied to upstream performance, certification or payment checked against the applicable statutory restrictions; do not assume that a main-contract certificate can indefinitely postpone your contract payment.

Keep the release request, service record, notices and actual receipts together, and pursue an overdue balance without losing sight of finality or limitation deadlines.

### Track the request through to payment

Use a separate row for each project and release stage in your retention record. Enter the contractual trigger, supporting evidence, amount requested and payment allocated to that stage.

Attach the relevant completion or defects evidence to your request. Ask for the contractual and factual basis of any refusal. A reminder does not automatically satisfy an application or notice requirement, so follow the actual payment provisions.

Our [Final account preparation and assessment](<https://www.quantsurv.com/quantity-surveying#client-types>) prepares the balance reconciliation and evidence supporting the release application. For a contested position: Our [Retention recovery](<https://www.quantsurv.com/claims/retention-recovery>) examines the release terms, supporting evidence and the amount still unpaid.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)
