# Schedule of rates (SOR): definition and example

A list of rates for types of work, without firm quantities, used to price and value work as it is measured.

By [Jack Butler-Kettle](<https://www.quantsurv.com/about#who-we-are>) · Updated 30 September 2026

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

## What it means in practice

Read this alongside [NRM 2: Detailed measurement for building works](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>).

A schedule of rates provides prices for defined units of work. The descriptions, measurement rules and included allowances determine how a rate is used. A rate for one specification or working condition may not be appropriate for a materially different item.

Retain the agreed descriptions as well as the numbers. [Variation recovery](<https://www.quantsurv.com/variations/services/variation-recovery>) can help connect measured changes to the applicable valuation basis.

## Worked example

### The facts

A schedule prices a defined type of painting at £12 per square metre.

### What happens

1.  The subcontractor measures 50 square metres of matching instructed work.
    
2.  It checks that preparation and access conditions fall within the rate's description.
    

### What this shows

The illustrative £600 valuation follows only after confirming that the rate applies to the work measured.

## Sources

1.  [NRM 2: Detailed measurement for building works, UK 2nd edition, October 2021 (reissued October 2022 as RICS practice information)](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>). RICS.