# Preliminaries: definition and example

The costs of running the site that do not belong to one item of work, such as supervision, welfare, access and site plant.

By [Jack Butler-Kettle](<https://www.quantsurv.com/about#who-we-are>) · Updated 30 September 2026

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

## What it means in practice

Read this alongside [NRM 2: Detailed measurement for building works](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>) and [SCL Delay and Disruption Protocol](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>).

Preliminaries are project-related costs that support delivery rather than one measured item of work. Some are time-related, such as supervision or hired accommodation; others may be fixed. That distinction matters when considering a change or delay because not every preliminary increases with duration.

Separate fixed and time-related costs in your records. [Delay and disruption recovery](<https://www.quantsurv.com/delay-and-disruption/services/delay-disruption-recovery>) can help explain which additional costs are connected to the event.

## Worked example

### The facts

A package has a one-off mobilisation cost and weekly supervision costs.

### What happens

1.  A delay extends supervision, but no second mobilisation takes place.
    
2.  The subcontractor records the additional supervision separately from the original fixed cost.
    

### What this shows

An extended duration does not justify charging every preliminary item again.

## Sources

1.  [NRM 2: Detailed measurement for building works, UK 2nd edition, October 2021 (reissued October 2022 as RICS practice information)](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>). RICS.
2.  [Delay and Disruption Protocol, 2nd edition, February 2017](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>). Society of Construction Law.