# Notice of adjudication: definition and example

The notice identifying the dispute to be adjudicated and the remedy sought, starting the applicable procedural timetable.

By [Jack Butler-Kettle](<https://www.quantsurv.com/about#who-we-are>) · Updated 30 September 2026

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

## What it means in practice

Read this alongside [paragraph 5 of Part I of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/5>) and [paragraph 7 of Part I of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/7>).

The notice identifies the dispute being referred and the remedy sought. Under the England-and-Wales Scheme, the referral must follow within seven days of the notice. Appointment and service need careful coordination; a poorly defined notice can create jurisdictional or procedural disputes.

Check the applicable rules before starting the clock. A [claim viability review](<https://www.quantsurv.com/claim-viability-review>) can organise the underlying claim, while formal procedure may require specialist advice.

## Worked example

### The facts

A subcontractor is considering referring a disputed valuation to adjudication.

### What happens

1.  It defines the dispute and requested decision from the existing exchanges.
    
2.  It checks that the referral documents and appointment arrangements can meet the applicable timetable.
    

### What this shows

The notice starts a procedural sequence; it should not be sent as a casual payment reminder.

## Sources

1.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part I, para 5 (Notice of intention to seek adjudication)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/5>). legislation.gov.uk.
2.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part I, para 7 (Notice of intention to seek adjudication)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/7>). legislation.gov.uk.