# Loss and expense: definition and example

The money you lose when the job is delayed or disrupted by events your contract puts at the other side's risk.

By [Jack Butler-Kettle](<https://www.quantsurv.com/about#who-we-are>) · Updated 30 September 2026

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

## What it means in practice

Read this alongside [SCL Delay and Disruption Protocol](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>).

A loss-and-expense claim seeks compensation under the relevant contractual provisions for the financial effect of qualifying events. More time to complete does not automatically produce a money entitlement. The event, conditions, causal link and supported amount need to be considered separately.

Keep cost records connected to specific events and periods. [Delay and disruption recovery](<https://www.quantsurv.com/delay-and-disruption/services/delay-disruption-recovery>) can help distinguish additional cost from the original priced work.

## Worked example

### The facts

Late access keeps a site supervisor on a package longer than planned.

### What happens

1.  The subcontractor checks whether the event qualifies under its loss-and-expense terms.
    
2.  It links the additional supervisor cost to the affected period and considers any costs avoided.
    

### What this shows

A supported calculation explains the additional loss without assuming that every cost during the delay is recoverable.

## Sources

1.  [Delay and Disruption Protocol, 2nd edition, February 2017](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>). Society of Construction Law.