# Daywork: definition and example

A method of valuing work using recorded labour, plant and materials under agreed rates and rules.

By [Jack Butler-Kettle](<https://www.quantsurv.com/about#who-we-are>) · Updated 30 September 2026

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

## What it means in practice

Read this alongside [NRM 2: Detailed measurement for building works](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>).

Daywork values work by specified resource inputs and agreed rates or rules. A signed sheet may acknowledge the resources used without accepting liability, the instruction or the final price. The subcontract determines when daywork is appropriate and how additions or mark-ups are calculated.

Record the instruction as well as labour, materials and plant. [Variation recovery](<https://www.quantsurv.com/variations/services/variation-recovery>) connects those records to the applicable payment basis.

## Worked example

### The facts

Two operatives each spend four hours on instructed extra work at an assumed agreed rate of £30 per hour.

### What happens

1.  The sheet records eight labour hours, the work location and the instruction reference.
    
2.  The subcontractor checks any separate material charges and agreed additions.
    

### What this shows

The labour calculation is £240; the signed sheet alone does not establish acceptance of every element of the claim.

## Sources

1.  [NRM 2: Detailed measurement for building works, UK 2nd edition, October 2021 (reissued October 2022 as RICS practice information)](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>). RICS.