# Activity schedule: definition and example

In an NEC contract under Option A or C, the list of activities, each with a price, that makes up your price.

By [Jack Butler-Kettle](<https://www.quantsurv.com/about#who-we-are>) · Updated 30 September 2026

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

## What it means in practice

Read this alongside [the NEC Dictionary of Terms](<https://www.neccontract.com/resources/dictionary>).

An activity schedule connects the price to identifiable parts of the work. It is not the same as the programme, which explains sequencing and timing. NEC Option A and Option C use the schedule differently, so do not assume the same payment assessment applies to both.

Check how activities are described and when they qualify for payment. A [pre-signing contract review](<https://www.quantsurv.com/contract-review/services/pre-signing-contract-review>) can examine whether the proposed payment structure matches your package.

## Worked example

### The facts

An electrical subcontractor prices first fix at £8,000 and testing at £2,000 under an assumed unamended Option A arrangement.

### What happens

1.  It checks the contractual completion requirements for each activity.
    
2.  First fix is complete at assessment, but testing has not started.
    

### What this shows

The £8,000 completed activity is considered under the payment rules; the whole £10,000 is not automatically payable.