# My quote was accepted six months after I priced it

We priced the package in the winter, heard nothing, and now an order has arrived at our old price with our materials much dearer.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Check whether the quotation was an offer, its validity wording and whether later correspondence or conduct already formed an agreement. A later order does not automatically settle which price applies. An expiry date is important evidence, but formation and any later extension need checking together.

Starting work can affect the terms you are taken to have accepted. Resolve the price and scope in writing before mobilising where possible, and obtain advice promptly if work has started or the parties disagree.

## What do I need to do?

1.  Check the quotation's validity period, base date and any communications about acceptance.
2.  Obtain current supplier prices and quantify the change.
3.  Clarify the agreed price and any proposed adjustment mechanism in writing before committing further expenditure.
4.  Seek advice if acceptance or existing obligations are disputed; do not assume the quotation can simply be repriced after a binding agreement.

To have this done for you, see our [Price-rise risk controls setup](<https://www.quantsurv.com/claims#client-types>) and [Contractual price increase recovery](<https://www.quantsurv.com/claims/contractual-price-increase-recovery>) services.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)