# They say my price rises are my problem because I'm on a fixed price

There's no fluctuations clause, our suppliers have all put their prices up, and the other party says that's our problem.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

On the rise itself, the other party is usually right. A fixed price puts the risk of price movements on you, and a steep rise in costs does not change the price or end the contract. Asking for help as goodwill sometimes works, but it is a favour you negotiate, not something you are owed.

What gets missed is the part of the rise that is not yours. Work the other party changed can be valued as a variation, and if it was done later or in different conditions it may be valued at today's prices. If its delay pushed your work into dearer months, the extra cost can go into a loss and expense claim. Each depends on your contract's terms and on records kept at the time. Miss them and you carry the whole rise.

## What do I need to do?

1.  Separate ordinary fixed-price exposure from changed work and cost attributable to a potentially compensable delay.
2.  Identify the contractual valuation or adjustment basis for each item.
3.  Support the periods and price differences with instructions, tender records, invoices and correspondence.
4.  Check notices and remove overlaps before submitting the supported items; overspend alone does not establish entitlement.

To have this done for you, see our [Contractual price increase recovery](<https://www.quantsurv.com/claims/contractual-price-increase-recovery>) and [Price-rise risk controls setup](<https://www.quantsurv.com/claims#client-types>) services.