Source: https://www.quantsurv.com/price-rises/faq/withdraw-quote-prices-rise
Content format: Markdown version of the public page.
Content reviewed: 2026-10-09

# Can I withdraw my quote if prices rise before it is accepted?

You may be able to withdraw an unaccepted offer, but first establish what your quotation, tender conditions and subsequent communications have already agreed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

A quotation may be an offer capable of acceptance, an invitation to negotiate or part of a wider agreement. Check its wording, validity period, tender rules, any commitment to keep it open, orders, correspondence and conduct. A price rise does not by itself cancel an existing contract.

Where an offer remains revocable, withdrawal generally needs to be effectively communicated before acceptance, subject to the applicable rules. Obtain advice if an order, acceptance, work start or competing terms make formation uncertain. Do not assume that lack of a signature means there is no agreement.

State any revised price, validity, scope and inflation mechanism clearly and obtain agreement before committing resources. If a validity period has expired, check whether the parties extended, revived or otherwise accepted the proposal. A new base date only governs the agreed mechanism from that point; it does not automatically compensate for inflation that has already occurred.

Our [Tender pricing and submissions](<https://www.quantsurv.com/quantity-surveying#client-types>) records quotation validity, assumptions and the current cost basis; legal questions about acceptance need appropriate advice.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)
