# What is a price fluctuation clause in construction?

A price fluctuation clause adjusts your price when named costs move after a base date, so a rise is paid rather than absorbed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## The answer

A price fluctuation clause adjusts your price when named costs move after a base date, so a rise is paid rather than absorbed. It is also called a price escalation clause or a price adjustment clause. Without one, a fixed price leaves the risk of rising costs with you.

A clause that works answers five questions. Which costs are adjusted: everything, or only named materials such as steel, copper or timber? From what date: the base date, the date your prices were fixed to? By what measure: invoices against your tender quotes, or a published index? From what threshold: every movement, or only a change above a set percentage? And what notice: must you notify each rise, and by when? A clause usually works both ways, so your price comes down if costs fall.

Here is a plain-English example. The reinforcing steel price moves with the named steel index, from the base date of 1 March to the month of delivery. In this illustration, the clause ignores movements below 3%, but adjusts the full movement once that trigger is reached; 3% is not a deductible allowance. The subcontractor gives notice of each change within 14 days of the index being published.

The standard forms have their own versions: the JCT fluctuation options and NEC's Option X1. Your contract may choose one, amend one or delete them all. So read the price terms before you sign, and ask for a clause when the job is long or the materials are volatile. Our Price-rise risk controls setup service sets the price basis in your quotations and negotiates the clause before you sign.

Our [Tender pricing and submissions](<https://www.quantsurv.com/quantity-surveying#client-types>) identifies which price movements are allowed for in the offer and which remain a commercial risk.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)