# Can I recover price rises caused by the other party's delay?

Often yes, if your contract pays for the delay and you can show it pushed your work into dearer months.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Often yes, if your contract pays for the delay and you can show it pushed your work into dearer months. Under a JCT contract the route is usually a claim for direct loss and expense, for a matter the other party is responsible for. Under an NEC contract it is usually a compensation event, assessed on Defined Cost, the NEC's defined measure of your costs.

Either way you have to show three things. First, that the delay was the other party's responsibility under the contract. Second, that it pushed particular purchases or labour into a later, dearer period. Third, what the difference cost, usually the invoiced price against the price you would have paid when the work was programmed.

The delay itself, how long and whose, comes from the programme records. The money comes from the tender prices, the supplier increase notices and the invoices. If your contract also has a fluctuations clause, take care not to claim the same rise twice, once under each.

Building the money side of a rise caused by delay is part of our [Contractual price increase recovery](<https://www.quantsurv.com/claims/contractual-price-increase-recovery>) service.