# Can I claim for price rises on a fixed-price contract?

Usually not for the rise itself, but you may still recover the part the other party caused.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Usually not for the rise itself, but you may still recover the part the other party caused. A fixed price puts the risk of price movements on you, and a steep rise in costs does not change the price or end the contract.

Work the other party changed may be valued as a variation at current prices. That depends on your contract's valuation rules allowing a new rate for changed work or changed conditions. Work its delay pushed into dearer months may form part of a loss and expense claim. Under an NEC contract it may be a compensation event, NEC's route to extra time and money. Both depend on your contract's wording and on records made at the time: the tender prices, the supplier increase notices and the invoices.

Beyond that, help is a negotiation. Some main contractors share an exceptional rise to keep a subcontractor on site, but that is their commercial choice, not something you are owed.

For the next job, the fix is in the quotation: a base date, a validity period and the volatile materials on an adjustment basis.

Separating the recoverable part of a rise and claiming it is our [Contractual price increase recovery](<https://www.quantsurv.com/claims/contractual-price-increase-recovery>) service.